Run prototype and pilot production builds (EVT, DVT and PVT)
Hardware is built several times before mass production. Each build has a purpose and exit criteria: first the design works, then it is right, then the factory can make it.
About 20-60 daysEvergreenLast reviewed 5 November 2026
Who this applies to
- Skills it builds
- Delivery and executionTechnical and AI fluency
- PM types
- Hardware or IoT
- Product types
- All
- Starting points
- All
- Ways of working
- All
- Experience
- All
- Size of organisation
- All
Steps, by experience
Beginner (under 1 year)
- Learn the three builds: engineering validation (EVT), design validation (DVT) and production validation (PVT).
- For each build, write down what it must prove before the next one starts.
- Agree how many units each build needs, including extras for testing and marketing.
- Track the issues found in each build and who is fixing them.
- Do not move to the next build until the exit criteria are met.
Intermediate (1 to 4 years)
- Plan the build schedule with time to fix issues between builds.
- Agree exit criteria for each build with engineering and the manufacturer.
- Shorten the build, test and fix cycle rather than squeezing the schedule.
Experienced (5+ years)
- Set build standards across products so schedules are comparable.
- Decide when an extra build is cheaper than shipping a known problem.
- Report build readiness to leadership with clear risks.
Who can do this
Owner: Product manager
Can be delegated to
- Hardware / manufacturing engineer or Tech Lead: Agree exit criteria and the build schedule
- QA / Tester or Hardware / manufacturing engineer: Run the tests for each build
Reviewed by: Hardware / manufacturing engineer, Tech Lead
Tool examples
- Jira
- Track issues by build, such as EVT or DVT.
- Confluence
- Write the exit criteria for each build on one page.
Definition of done
- Exit criteria written for each build
- Build quantities agreed
- Issues tracked to closure before the next build
Common pitfalls
- Calling a build DVT when the design is still changing
- Too few units for testing
- Squeezing the schedule instead of fixing faster
If you lead the team
What good looks like: Each prototype build has a clear purpose and exit criteria before the next one starts.
Ask your PM
- What must this build prove, and did it?
- What's blocking the move to the next build?
Warning signs
- Builds move on with known problems unresolved.
- Exit criteria are vague.